Expected Monetary Value

1395/06/5
09:24
امیرحسین ستوده بیدختی امیرحسین ستوده بیدختی
How should we identify the importance of risks?
Impact is closely related to importance. The impact on project objectives: time, cost, quality, and so on. It’s best if you convert them all into money. For example, if you have a penalty/award of €10K/day, the impact of a risk that reduces the duration of the project by 20 days would be 20days*€10K/day=€200K. 

Is it enough?
Let’s say you have the following two risks:
  • €200K impact, very unlikely to happen
  • €150K impact, likely to happen
Which one is more “important”? Probably the second one. 
We usually understand the importance of the risk based on its Expected Monetary Value (EMV):
EMV = probability * impact

How would you consider the probability, without making it too complex?


برچسب ها:Expected Monetary Value ،Value ،
نظرات

ادامه مطلب ادامه مطلب

مهندسی و مدیریت ساخت پروژه - Expected Monetary Value

مهندسی و مدیریت ساخت پروژه - Expected Monetary Value,مدیریت ساخت ,مدیریت پروژه, مدیریت پروژه های ساخت, مدیریت پروژه و ساخت,مدل سازی اطلاعات ساختمان,مدیریت ساخت
تمامی حقوق این وب سایت متعلق به مهندسی و مدیریت ساخت پروژه است. |طراحی و توسعه:امیرحسین ستوده بیدختی|
شبکه اجتماعی فارسی کلوب | Buy Website Traffic | Buy Targeted Website Traffic